Lots of concrete being poured this week.
Curb will be poured from Northside to Carroll. Work will be done in the bridge area and the sidewalks should be finished on Progress.
This week and next, crews will pour the trails between Winslow and Northside. Curb and gutter will be poured at Carroll Drive and grading will be finished between Aden and Carroll. Paving of the trail under the Progress Street bridge should be completed soon.
The weather hasn’t been kind to the construction crews this week. The 12″ water line is installed and tied in, but the grading and concrete work cannot continue until the rain stops. Rain, rain go away!
This week crews will test water lines. They will lay storm drain and build the road between Carroll and Aden. curb and gutter pouring continues.
We hope to have some pictures up this week.
Grading continues on Givens Lane. There will be no through traffic (only residents) on Givens between Aden Lane and Carroll Drive.
Retaining wall work continues.
On Wednesday, April 17, those who need to access Carroll Drive will use the Northside roundabout at Progress Street.
Crews continue to lay stone and grade Carroll Drive.
Next Wednesday, April 17 (or later), those who need to access Carroll Drive will use the Northside roundabout at Progress Street. Next week’s update will have more information.
Beginning April 8 and for the rest of the week the intersection of Givens and Carroll will be graded. As a result, there will be traffic interruptions in the area. Flaggers will be at the intersection to direct traffic, but it is best if travelers use an alternate route.
View Larger Map
Beginning Monday, April 1, Givens Lane will be closed between Carroll Drive and the entrance to Blacksburg Estates. This closure is expected to last one week. Those leaving Blacksburg Estates from Yale Drive, Princeton Road, Harvard Road, and Ferrum Circle will have to turn left on to Givens Lane and use the roundabout to the new Progress Street extension.
For more information, contact Brandon Steele at 540-961-1172.
